Kingston Pike Sidewalk at Willow Creek Golf Course – TDOT

TDOT and the Town of Farragut are implementing a TDOT Local Programs project to build a sidewalk on the south side of Kingston Pike along the Willow Creek Golf Course.  As a result of the scheduled work, FUD will be relocating approximately 2,200-ft of 12-inch Water Main.  FUD’s work is expect to occur between March – May 2018.  The TDOT construction schedule is expected to occur from February – June 2018.