S. Cedar Bluff Water Line Replacement Project (Phase 1)

FUD has planned the replacement of approximately 4,500-ft of water mains in the S. Cedar Bluff Subdivision.  The initial phase of the work will include the replacement of mains and service lines on Clearfield Rd, Clingmans Dr, and Elkmont Rd..  The project has been scheduled to improve system reliability and fire protection in the neighborhood.  Future phases of work will be extended on crossing streets.  We have a start date planned for next Wednesday, August 22.  Work will require potholing to locate the existing utilities and prevent damage.  Incidental work will require digging in yards, possible removal of bushes or shrubs in right of way, and cuts across the driveways in right of way.  We will replace the driveway cuts in kind with either asphalt pavement, concrete pavement, or gravel.  We will restore vegetation as work progresses.

S. CEDAR BLUFF WATER LINE REPLACEMENT PROJECT